Payment terms for bag orders from China: T/T, deposits and the balance

The deposit line on a custom-bag quotation is where most first-time buyers hesitate — and where the least reading gets done before money moves. The structure is simpler than it looks, and every part of it maps to a real stage of production: materials cut to spec, cartons packed to the buyer's label, and a vessel that sails on a date.

Published 24 November 2026 · Alice Bao, Harbour Bags

Short answer

The working default in the bag trade is T/T 30/70: a 30% deposit when the order is confirmed, and the 70% balance before the goods ship. Samples are paid upfront and commonly credited against the bulk invoice. Full-container orders can move to a letter of credit at sight, where the buyer's bank releases the balance only against shipping documents. The deposit is not a trust exercise — it buys materials that cannot be resold once they are cut to your specification.

StageWhat it isTypical structure
SamplePrototype built to your specPaid in full before sampling; credited against bulk once the order confirms
DepositOpens the production orderT/T 30% with order confirmation — releases material buying and reserves the slot
BalanceThe finished, packed goodsT/T 70% before shipment, after inspection passes
L/C at sightBank-guaranteed balanceFull containers; payment against documents when the goods are on board

Why a deposit exists at all

Custom bags are made to order in the strict sense. The shell fabric is dyed or coated to a Pantone reference, the webbing is woven in your colour, the hardware is plated to your finish, and the lining is cut to a pattern that exists only for your style. None of that inventory is resellable — a roll of purple 600D cut into panels for one buyer's backpack is scrap to every other buyer. The deposit funds exactly this exposure: material purchase and the production slot reserved on the line.

It also sets the clock. A factory's bulk lead time of 35–50 days does not start at the handshake; it starts when the deposit lands and the material buying begins. Fabric and hardware sourcing runs one to two weeks before a panel is cut, and the line slot is held against that date. This is why a late deposit does not shift the schedule neatly by the same number of days — it can push the order past a reserved slot and behind another buyer's run, which costs more than the delay itself.

T/T 30/70

What the 30 and the 70 actually map to

The 30% deposit roughly corresponds to what the factory must lay out before anything can ship: shell fabric, lining, webbing, zips and hardware, plus the slot reservation. The 70% corresponds to the value sitting in finished, packed cartons — goods already labelled to the buyer's brand, in cartons marked with the buyer's shipping marks, staged and ready for a vessel the buyer's side nominated.

Deposits outside the 20–40% band deserve a question in either direction. A 10% deposit means the factory is financing production largely on its own credit, which is sustainable only for a buyer it already trusts — expect it on a fifth reorder, not a first order. A 50% deposit means the buyer is financing more than the materials, and the extra should buy something concrete: a locked price, a locked slot, or a shortened lead time.

The deposit is also the natural point to fix everything downstream, because it is the moment the order becomes real. Quantity, the incoterm, the production schedule, the packing specification and the inspection window should all be stated in the same message that acknowledges the deposit — changes after materials are cut stop being changes and become remakes.

Balance

Before shipment, not on arrival — and why

Balance before shipment is the structure buyers most want to renegotiate, so it is worth spelling out the logic. Once the goods are produced, inspected, packed to the buyer's specification and staged at the port, they are unresellable inventory worth the full balance. The factory has converted its cash into goods that only one company in the world can use. Collecting the balance at that point — after the buyer's inspection has passed and before the container gates in — matches payment to exactly that moment.

The inspection window is what makes the sequence fair rather than one-sided. The right order runs: goods complete and packed → buyer's inspection (third-party or factory QC with a photo report) → balance wired → goods released to the forwarder. A buyer who wants more assurance than a report can send an inspector at the 80%-packed stage, before the balance is due — the timing costs a local day-rate, not a renegotiation of terms.

Balance on arrival inverts all of it. The goods are now in the buyer's physical possession in the destination market, and any dispute stops being a quality claim and becomes a payment negotiation between two companies on different continents. That is why almost no factory accepts it on a first order — and why buyers with a track record sometimes get it: the concession is bought with history, not with arguments.

L/C

L/C at sight: what it protects and what it costs

A letter of credit at sight replaces the buyer's wire with the buyer's bank's commitment: payment releases against documents — bill of lading, commercial invoice, packing list, and any certificates the credit requires — the moment they are presented clean. The practical protection is real: the balance does not move until the goods are demonstrably on board the vessel, and neither party has wired or waited on trust.

What an L/C does not do is inspect goods. Document compliance is not quality — a credit paid against a clean bill of lading has said nothing about the stitching inside the cartons. The inspection still has to happen before shipment, as it would under T/T. And the costs are easy to underestimate: issuance fees, advising fees, and the amendment friction when a detail changes, each charged by banks that bill per document.

That arithmetic is why L/C at sight earns its place on full-container orders and rarely on LCL. On a container-sized balance, the bank fees are a rounding error against the risk removed; on a small LCL shipment they can exceed the value of the protection. This is the usual market split: T/T 30/70 as the working default, L/C at sight available at the container end, and neither offered ceremonially on orders too small to justify either.

Schedule

How payment timing locks the production calendar

MilestoneTriggerWhat starts
Deposit receivedT/T 30% confirmed in the factory's accountMaterial buying, slot reservation; the 35–50 day clock starts here, not at signature
Materials in houseRoughly 7–15 days after depositCutting and sewing begin on the reserved slot
Goods complete & packedBulk finished, cartons markedInspection window opens; booking confirmed with the forwarder
Balance receivedT/T 70% after inspection passesGoods release to the forwarder; vessel gates in on the booked date
Vessel sailsDocuments issuedB/L released; under L/C, documents presented to the bank

Two delays cost more than they look. A deposit that lands a week late can push the order past a reserved line slot and behind another run, adding weeks rather than days — factories schedule in runs, not in single orders. And a balance wired after the booked vessel gates in means a missed sailing, a container sitting on demurrage at the port, and a rebooking fee; the goods were ready, the calendar was not. The fix on both is administrative: send the deposit confirmation the day it is wired, and start the balance paperwork when the inspection is booked, not after it passes.

Red flags

The payment details that catch buyers out

Pay to the account that matches the contract. Payments go to the company account named in the contract and quotation — never to a personal account, and never to a different company name "because our accountant is travelling". Account-change emails sent mid-transaction are the classic fraud vector in this trade; if the account changes, verify it by phone on a number you already held, not one from the email.

Fix the incoterm and the payment structure together. The two are quoted in one paragraph for a reason: an EXW price with a 70% balance before shipment is a different risk shape from a DDP price with the same split, because under DDP the seller holds the goods through import clearance as well. Changing one after the deposit should change the other.

Sample terms belong in the quotation. Whether the sample fee is credited against bulk, and on what conditions, is a one-line clause that costs nothing to write before sampling and a negotiation to settle after. Ask it before the first prototype, not when the bulk invoice arrives.

The four arguments this prevents

"We signed the contract in March, why has nothing moved?" The production clock starts at the deposit, not at the signature. Fix the deposit date and the schedule in the same message and the question never comes up.

"We want to pay the balance when the container lands." On a first order, that asks the factory to hold unresellable inventory across an ocean. Take the assurance from the inspection instead — it costs a day-rate and actually looks inside the cartons.

"The L/C was cheaper than we thought, let's use it for the 300-piece trial order." Bank fees scale with documents, not value; on small orders they cost more than the risk they remove. T/T with a pre-shipment inspection does the same job at LCL size.

"The account changed, the finance email said so." Verify by phone on a number held before the email. Every mid-transaction account switch deserves one awkward phone call, whatever the reason attached.

At quotation we state the term, the payment structure and the schedule in the same paragraph — T/T 30/70 as the standard structure, L/C at sight on full-container orders, sample fees credited against the confirmed bulk. Three lines, and most of the arguments above never get written.

Questions

Frequently asked

Is a 30% deposit standard for custom bag orders?

Yes — T/T with a 30% deposit and 70% balance before shipment is the working default in the bag trade, because the deposit roughly matches the cash the factory must lay out before anything can ship: fabric, webbing, hardware and lining are all bought or cut to the buyer's specification and cannot be resold. Deposits outside the 20–40% band deserve a question: much lower and the factory is financing production on its own credit; much higher and the buyer is financing more than the materials.

Can I pay the balance after the goods arrive?

Almost no factory accepts balance-on-arrival for a first order, and the reasoning is structural rather than stubborn. Once the goods are packed, labelled to the buyer's spec and staged at the port, they are unresellable inventory worth the full 70%. Balance before shipment keeps the claim structure clean: the buyer inspects, pays, and the goods release; after arrival the factory has no leverage except a new negotiation on every reorder.

What does an L/C at sight actually protect?

It protects the buyer's deposit: the issuing bank commits payment against documents — bill of lading, invoice, packing list, inspection or origin papers as required — so the balance only moves when the goods are demonstrably on the vessel, and the buyer's money is not wired before that proof exists. It does not inspect the goods; document compliance is not quality. Bank fees and amendment friction are why it earns its place on full-container orders and rarely on LCL.

Are sample fees refunded when the bulk order is placed?

Commonly, yes — at Harbour Bags the sample fee is credited against the bulk invoice once the order is confirmed. The fee exists to filter tyre-kickers and cover the pattern-maker's time; once there is a real production order behind it, keeping the fee would serve no purpose. Ask the question before sampling rather than after, and get it in the quotation.

What payment methods do Chinese bag factories accept?

Bank telegraphic transfer (T/T) is the main channel for order payments. Samples and small charges often move by PayPal or Western Union for speed, at the sender's cost. Escrow platforms appear in retail contexts but are rare in B2B manufacturing, and letters of credit appear at the top of the market on full-container orders. Whatever the channel, pay to the company account matching the contract — never to a personal account, even with a plausible reason attached.

Every quotation states the term, the payment structure and the schedule in one paragraph.

T/T 30/70 as the standard structure; L/C at sight on full-container orders; sample fees credited against the confirmed bulk order.